InterMoor completes disconnection contract for FPSO offshore Angola

InterMoor, an Acteon company, has successfully completed offshore operations for the disconnection and laydown of risers and mooring lines on a major floating production, storage and offloading (FPSO) facility offshore Angola. InterMoor won the contract in March 2014 and completed the work on budget, on schedule and with zero incidents in December 2014.

Project specifics

The project had two phases: Phase 1 concluded with the disconnection of all 20 risers and umbilicals from the FPSO facility and their placement on the seabed in accordance with the laydown agreement; in Phase 2, InterMoor disconnected all 12 mooring lines and placed them on the seabed while the FPSO was held in place by station-keeping vessels. InterMoor provided the station-keeping procedure and Tow Masters onboard the FPSO.

The initial contract scope included project management, engineering and offshore execution. InterMoor devised multiple methods for disconnection, including the use of clamps to take the load off the risers using the offshore construction vessel (OCV) and either disconnecting or cutting the hang off on the FPSO to lower the risers. The subsea riser clamp design and fabrication were added to the contract once the project progressed. The clamps were designed by Houston-based Acteon company, 2H Offshore, and fabricated in InterMoor’s facility in Morgan City, Louisiana.

Comment from the project manager

João Ruiz, Project Manager, InterMoor, said, “The successful completion of this project underlines our global reach and demonstrates the specific skills we provide for operations offshore West Africa. InterMoor was selected as the ideal candidate for the project because of our leading position as a mooring, foundations and subsea services provider for rig moves and mooring services, our decommissioning experience and our ability to provide local support from our operations base in Angola.”


Adapted from press release by Cecilia Rehn

Published on 02/04/2015


Get your FREE Oilfield Technology magazine »

Get your FREE trial of Hydrocarbon Engineering magazine »

Get your FREE trial of World Pipelines magazine »


 
 

Related articles

BMT supplies IMMS for Stampede TLP in the US Gulf of Mexico

BMT has been selected by Hess Corporation to supply an IMMS for the Stampede Tension Leg Platform (TLP) in the US Gulf of Mexico.

New spooling winches to support offshore mooring operations

Global Maritime Deep Sea Mooring has signed winches deal with Perth-based Green Monster Offshore.

InterMoor completes contract

InterMoor has successfully completed a mooring and foundation installation campaign for bpTT’s Juniper gas project offshore Trinidad and Tobago.

Bridon acquire the moorings business of ScanRope

Today Bridon have acquired the moorings business of ScanRope from the Parker Hannifin Corporation transferring deep-water assets to Bridon Holdings Limited.

Recommend magazines

  Oilfield Technology