Elements Green Deutschland GmbH has signed a grid connection agreement with transmission system operator TenneT Germany for its large scale battery energy storage (BESS) project in Stadorf, Lower Saxony. With a planned output of 400 MW and a storage capacity of 1600 MWh, Stadorf ranks among the largest battery storage projects in Germany.
Following the signing of the connection construction agreement in October 2026, the grid connection agreement marks a further significant step towards delivering the project. Together, the two agreements establish the key contractual framework for construction and subsequent operation of the grid connection.
The BESS will have a storage duration of four hours and will be connected directly to the extra-high-voltage grid. It will be able to store electricity during periods of high generation or low demand and release it back to the grid when needed.
Stadorf will make an important contribution to integrating renewable energy, increasing the flexibility of the power system and making efficient use of existing energy infrastructure.
Michael Zimmermann, Managing Director of Elements Green Deutschland, commented: “Signing the grid connection agreement marks another milestone for Stadorf. Together with the connection construction agreement, we now have the key contractual foundations in place for connecting this 400 MW project to the grid. This is significant progress for Elements Green and underlines our ability to advance complex energy infrastructure projects of this scale.”
Stadorf is part of Elements Green’s extensive German battery storage pipeline. The company is developing several large scale battery storage projects for connection to the extra-high-voltage grid and is pursuing a long-term strategy as an integrated developer, investor, and operator of energy infrastructure.
Zimmermann added: “Germany needs not only additional renewable generation capacity but, above all, the high-performance and flexible infrastructure to make the energy transition a technical and economic success. Large scale BESS such as Stadorf will play a central role in this.”
With the key grid connection agreements now in place, Elements Green is focusing on the next stages of technical and commercial implementation. This includes detailed planning of the grid connection infrastructure, preparations for construction, and continued co-ordination with the project and technology partners involved.
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
Energy Global’s Autumn 2026 issue
The Autumn issue of 2026 is available now! The new issue begins with a regional report on Asia Pacific, looking at the region’s transition from building capacity to building systems. The issue also explores topics such as offshore wind foundations, solar maintenance, training the new workforce, inspection & maintenance, and more! With insights from experts such as Everllence, BW Ideol, EM&I, Watson Farley & Williams, and many more, make sure to check out this issue now.