TenneT commences cable production for offshore wind platforms
Published by Theodore Reed-Martin,
Editorial Assistant
Energy Global,
Production at LS Cable in Donghae, South Korea, has started. The new cables with a voltage of 525 kV raise the transmission capacity for offshore wind energy to a new voltage level. They make it possible to transmit 2 GW of direct current over long distances with low losses. Up to now, 320 kV cables have been used for offshore grid connections, for example in TenneT's 900 MW projects.
The start of cable production is part of the framework agreement that TenneT concluded with the consortium consisting of the Jan De Nul Group, LS Cable & Systems and Denys in May 2023. The contract covers the production and installation of four 525 kV DC cable systems for the TenneT grid connection projects in the North Sea. The first DC cables produced by the South Korean cable manufacturer LS Cable are intended for the BalWin4 and LanWin1 grid connection projects.
In addition to a positive and negative pole, an additional cable - a so-called metallic return conductor - will be laid for both grid connections in future, which will ensure that electricity can continue to flow in the event of maintenance or repair work. The three cables will be supplemented by an additional communication cable.
A total of 1650 km of cable will be produced for the BalWin4 and LanWin1 projects (route length per project: 275 km, of which 165 km are submarine cables and 110 km are land cables). The inner conductor is made of copper, which makes the cables real heavy-weights. The submarine cables alone weigh around 76 kilograms per metre. The total weight for the submarine cable (plus/minus pole) is therefore around 25 000 tonnes per project – a logistical challenge.
Production of the cables will be completed in 2028. Cable laying at sea is expected to begin in 2H26. The Jan De Nul Group will use the extra-large cable-laying vessel ‘Fleeming Jenkin’, which was specially designed and ordered for the transport and laying of the 525 kV DC cables on the seabed.
The Construction of the land cable is also scheduled to start in 2H26 by the construction company Denys, with work being carried out as usual using the open trench method with a cable trench and the closed trench method using horizontal drilling. These will be used to cross bodies of water and existing infrastructure such as railway lines, dykes, roads and the like.
BalWin4 is scheduled to go into operation in 2029, LanWin1 in 2030.
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
Energy Global's Spring 2024 issue
The Spring 2024 issue of Energy Global starts with a guest comment from Field on how battery storage sites can serve as a viable solution to curtailed energy, before moving on to a regional report from Théodore Reed-Martin, Editorial Assistant, Energy Global, looking at the state of renewables in Europe. This issue also hosts an array of technical articles on electrical infrastructure, turbine and blade monitoring, battery storage technology, coatings, and more.
Read the article online at: https://www.energyglobal.com/wind/31052024/tennet-commences-cable-production-for-offshore-wind-platforms/
You might also like
Financial close for Baltyk 2 and Baltyk 3
Equinor and Polenergia, the project’s joint venture partners, have reached financial close for the Baltyk 2 and Baltyk 3 projects.