A new battery energy storage system (BESS) being built on the former coal power station at Fiddler’s Ferry has passed a major milestone, with the installation of key electrical equipment.

The site is owned by SSE Renewables, with infrastructure specialists OCU Energy and Fluence building the 150 MW BESS. When complete, it will be capable of providing power for approximately 250 000 homes for a two-hour period at a time.

An SSE Renewables spokesperson previously said: “Similar to our Ferrybridge project, our grid scale battery at Fiddler’s Ferry will be built on what was a former SSE-owned coal-fired power station and highlights the transition away from fossil fuels towards a net-zero future.”

Kiosk buildings, which will house electrical relays, switchgear, control panels, and communication systems, are now in place, fabricated by RSK Group companies AJ Engineering & Construction Services and Northern Engineering & Welding Co. (NEWCo).

AJ Engineering & Construction Services Pre-Construction Manager, Lee Binks, said: “When fully operational, the BESS site will store power for release back to the UK national grid when it is needed the most – helping to manage peaks of energy demand and supporting a transition away from fossil fuels.

“We have designed, fabricated and cladded two auxiliary transformer buildings and one portable relay room for the site in a modular format, reducing the time spent on site. These buildings provide compact, weatherproof enclosures that house the equipment that ultimately connects the battery system to the national grid. In addition to this, we have fabricated and erected the switch room, which is a structural steel portal frame building with insulated cladding.

“Usually, for the aux buildings and portable relay rooms, these types of small buildings are manufactured using glass reinforced plastic or brick and built on site. To speed up delivery and reduce complexity, we built them off-site using fabricated steel modules. They were then transported to the site and lifted into place, already cladded and ready for fit-out.”

Binks explained that because they are widely used in both the water and the en-ergy sectors, they are in high demand, and lead times for their procurement can be significant.

He concluded: “Having been built with steel and cladding, the kiosks were ready to be installed on site within six weeks. Normally this team of structural designers, detailers, fabricators, steel erectors and site management would have to do this on-site. By building the kiosks off-site, we have avoided adding further complexity to an already busy construction site.”

Fellow RSK company, Acies, carried out the connection design on the structural frame for the switch room, working in collaboration with AJ Engineering while it carried out the modelling of the building.

With the kiosks in place, OCU Group will begin the fit-out process of the internal equipment that will connect the site to the national grid. It is expected to be operational in 2027.

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global’s Autumn 2026 issue

The Autumn issue of 2026 is available now! The new issue begins with a regional report on Asia Pacific, looking at the region’s transition from building capacity to building systems. The issue also explores topics such as offshore wind foundations, solar maintenance, training the new workforce, inspection & maintenance, and more! With insights from experts such as Everllence, BW Ideol, EM&I, Watson Farley & Williams, and many more, make sure to check out this issue now.