Minesto undertakes final quayside assembly of Dragon 12
Published by Jessica Casey,
Editor
Energy Global,
Minesto, a leading ocean energy developer, has completed the manufacturing of the Dragon 12 wing and started system integration at quayside in Uddevalla port, Sweden. The quayside completion of the kite enables an efficient shipment directly to Minesto’s tidal energy production site in Vestmannasund, Faroe Islands.
Minesto has now transported the first completed Dragon 12 wing to the port of Uddevalla for integration of subsystems and further transport to the production site in Vestmanna, Faroe Islands. Final system integration at quayside is logistically cost effective and reduce the need for complex and expensive transport of the large wing.
The wing, spanning 12 m, is a key component in the Dragon 12 system to which all other modules connect. All subsystems, including the 1.2 MW power take off, steering pods, and control system are being prepared for integration.
“The Dragon 12 wing has a very efficient and uncompromised hydrodynamic design. It is practically a scale-up of the Dragon 4 wing, with some adjustments to allow for tighter turns and to cater for the higher forces resulting from a larger system,” said Bernt Erik Westre, CTO of Minesto.
The manufacturer of the wing is Swedish composite specialist, Elitkomposit. The cutting-edge supplier of advanced composite components is often contracted by high-tech industries such as the defence and space industry. Elitkomposit has previously delivered the wings for DG100, Dragon 2 and Dragon 4 along with other composite assemblies – thus been able to integrate previous experience into the utility scale Dragon 12 wing, as well as the completion of the D12 rudders and elevators.
“The organic shape and the high loads involved makes this wing one of the most advanced yet robust components we ever delivered. We are excited to contribute to new technologies in the renewable energy sector,” added Andreas Simonsson, Senior Design Engineer at Elitkomposit.
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
Energy Global's Autumn 2023 issue
The Autumn 2023 issue of Energy Global hosts an array of technical articles focusing on green hydrogen, wind installation technology, blade monitoring solutions, and more. This issue also features a regional report looking at some key renewables projects in Australia.
Read the article online at: https://www.energyglobal.com/other-renewables/03102023/minesto-undertakes-final-quayside-assembly-of-dragon-12/
You might also like
Full Circle renews full-scope contract to service EWT turbines
Full Circle Wind Services has secured the renewal of its full-scope operations and maintenance contract for 41 turbines across the UK.