First electrolyser modules have arrived at RWE’s hydrogen plant in Lingen

Published by , Editorial Assistant
Energy Global,


Nine months after the ground was broken for RWE’s pilot hydrogen plant, the first electrolyser modules for generating hydrogen have arrived at the construction site at the Emsland gas-fired power station, Germany.

During a four-day period, eight pressurised alkaline electrolyser modules manufactured by Sunfire, with a capacity of 10 MW, arrived at the site on articulated lorries. A gantry crane on rails lifted the components, each weighing 15 t, into place in a specially erected hall where they will be combined in groups of four to create stacks approximately 10 m high.

Sopna Sury, COO Hydrogen RWE Generation, commented: “Following months of preliminary work, it is exciting for everyone to see the pilot plant taking shape. With the arrival of the first electrolyser, we have come another step closer to our goal of producing green hydrogen. Once it has been commissioned, the Lingen plant (Germany) will help us to build up experience with two technologies for the subsequent operation of large scale electrolysers.”

In the coming weeks, engineers will install the 10 MW pressurised alkaline facility within the pilot plant and integrate it into the infrastructure at the Emsland gas-fired power station. A Linde PEM electrolyser with capacity of 4 MW will be delivered to an adjacent building in the near future to complete the pilot plant.

The facility is expected to go into operation this Autumn. Using electricity from renewables, it will be able to generate up to 290 kg of green hydrogen every hour. The hydrogen will be fed into a public hydrogen network or be mixed with gas as a climate neutral fuel for turbines at the power plant. In the future, it could also be used to supply the mobility market and the hydrogen-ready gas turbine being planned for construction in Lingen by RWE and Kawasaki.

The German state of Lower Saxony is providing €8 million of funding for the project.

The Lingen location plays a key role in RWE’s hydrogen strategy: just a few metres from the pilot hydrogen plant, the company plans to set up its first large scale electrolyser facility as part of the GET H2 project. Its capacity will then be expanded in 100 MW increments to 300 MW by 2026. The objective of GET H2 is to work with partner entities to start building up a supraregional hydrogen infrastructure.

When it comes to hydrogen, RWE has all the possibilities under one roof: from green electricity production to expertise in producing and storing green hydrogen, and its supply and trading business that can make the fuel available to meet the needs of industrial customers. RWE is currently working with high-powered partners on more than 30 hydrogen projects.

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Spring 2023 issue

The Spring 2023 issue of Energy Global hosts an array of technical articles focusing on offshore wind, solar technology, energy storage, green hydrogen, waste-to-energy, and more. This issue also features a regional report on commodity challenges facing Asia’s energy transition.

Read the article online at: https://www.energyglobal.com/other-renewables/31032023/first-electrolyser-modules-have-arrived-at-rwes-hydrogen-plant-in-lingen/?yptr=yahoo

You might also like

 
 

Embed article link: (copy the HTML code below):