Thistle Wind Partners commences site surveys for ScotWind projects

Published by , Editor
Energy Global,


Thistle Wind Partners (TWP) has launched seabed surveys for its two ScotWind projects – the 1 GW Ayre offshore wind farm (a floating wind project to the east of Orkney) and the 1 GW Bowdun offshore wind farm (a fixed-foundation project off the coast of Aberdeenshire).

G-tec is leading the first phase of the work, which is the geophysical surveying of the seabed at both sites (leasing zones NE2 and E3), from March – October 2023. G-tec is supported by GAC UK’s Aberdeen and Orkney offices for vessel logistics, while Cathie (headquartered in Newcastle) is providing advisory services.

Over the next seven months, the survey vessel will cover an area of almost 400 km2, as it uses cutting-edge technology to collect data on the structure of the seabed at both project sites. G-tec technical experts will conduct advanced processing of the data, which will then feed into ground modelling studies from October onwards, while metocean surveys begin around the same time..

With TWP’s engineering team expected to complete their pre-FEED phase for the two projects by mid-2024, a second round of geophysical and geotechnical studies is planned for next year to inform the FEED for the wind farms.

“We are comfortable with the pace of development of the two projects and the schedule we have in place,” commented Ian Taylor, Project Director at TWP. “We plan to enter the construction phase in 2029, and like all ScotWind developers, we do get questions about why we have chosen a particular timeframe.

“Bearing in mind that we have a floating wind project in the mix, we are keen to leverage the learnings and enhanced designs and technologies that will be available by the end of the decade. There are still many technical challenges ahead for floating offshore wind. In tandem, each year gives us greater certainty that the local supply chain and port infrastructure will be ready.”

This summer, TWP continues the bird and marine mammal studies that were launched by contractor APEM in March 2022. Altogether, these studies will extend over a two-year period.

Taylor concluded: “We are investing in some of the most advanced monitoring techniques for our environmental studies, such as APEM’s LiDAR technologies for measuring bird flight heights. Taking the time to gather the best data for our final designs ensures that our wind farms have the most harmonious relationship with marine life and other maritime industries.”

The final investment decision for both the Ayre and Bowdun projects is scheduled for 2028 (if consenting is achieved in 2025).

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Spring 2023 issue

The Spring 2023 issue of Energy Global hosts an array of technical articles focusing on offshore wind, solar technology, energy storage, green hydrogen, waste-to-energy, and more. This issue also features a regional report on commodity challenges facing Asia’s energy transition.

Read the article online at: https://www.energyglobal.com/wind/06042023/thistle-wind-partners-commences-site-surveys-for-scotwind-projects/

You might also like

 
 

Embed article link: (copy the HTML code below):