Iberdrola installs Baltic Eagle Monopiles

Published by , Editorial Assistant
Energy Global,


Iberdrola has successfully installed all 50 monopiles for the Baltic Eagle offshore wind farm together with its partner Van Oord. The next step in the ongoing construction phase now involves the installation of the transition pieces. These were manufactured by the Spanish company Windar Renovables and temporarily stored in the port of Mukran. The transition pieces are the connecting element between the monopile and the tower of the wind turbine. The installation of the wind farm's internal cabling by Van Oord is planned for the end of 2023.

Iberdrola installs Baltic Eagle Monopiles

The construction of Baltic Eagle is proceeding according to plan

The monopiles were made by the Rostock-based company EEW SPC. Afterwards, they were transported floating from the port of Rostock to the Baltic Eagle offshore construction field. They were then positioned with the help of Van Oord’s heavy-lift installation vessel Svanen. The monopiles with a diameter of 8.75 - 9 m and a length of between 75 - 90 m were then driven into the seabed. They ensure that the wind turbines are securely anchored in the seabed.

"With the installation of the monopiles, we have reached another step in the construction of Baltic Eagle," commented Iris Stempfle, Managing Director of Iberdrola Germany's Offshore Division. "Above all, I would like to thank the responsible teams very much for their unremitting efforts. Everyone went the necessary extra mile to be able to successfully complete this intensive project phase."

The monopiles were manufactured in Rostock by the company EEW SPC. Above all, direct access to the German Baltic Sea enabled the uncomplicated transport to the wind farm. The international companies involved in the construction of Baltic Eagle have production facilities in five European countries, including Germany, Spain, Denmark, the Netherlands, and Belgium.

Iberdrola‘s Baltic Hub

With a production capacity of 476 MW, Iberdrola's Baltic Eagle offshore wind farm will supply approximately 475 000 households with renewable energy while reducing carbon dioxide emissions by approximately 800 000 tpy. The park is scheduled to be fully operational by the end of 2024. Baltic Eagle is the second of three large-scale projects in Germany. Iberdrola already operates the 350 MW Wikinger wind farm and is developing the 300 MW Windanker project, which will be completed in 2026. Together, these offshore wind farms form Iberdrola's so-called Baltic Hub. It will have a total capacity of more than 1.1 GW in 2026, with combined investment of around €3.7 billion.

 

 

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Summer 2023 issue

The Summer 2023 issue of Energy Global hosts an array of technical articles focusing on alternative fuels, battery storage solutions, solar optimisation, and more. This issue also features a regional report on the recent developments in the European renewables market.

Read the article online at: https://www.energyglobal.com/wind/12092023/iberdrola-completes-installation-of-all-50-monopiles-at-baltic-eagle-offshore-wind-farm/

You might also like

 
 

Embed article link: (copy the HTML code below):