Jan De Nul Group installs wind turbine for TPC

Published by , Assistant Editor
Energy Global,


Jan De Nul’s Offshore Jack-Up Installation Vessel Taillevent successfully installed the very first Hitachi turbine onto its jacket foundation for Taiwan Power Company (TPC).

With the first wind turbine installation completed, the project team will proceed with the commissioning process, along with the final termination of the subsea cable inside the tower.

The TPC Offshore Wind Farm near Fangyuan, eight km off the West coast of Taiwan, will comprise in total 21 units of 5.2 MW wind turbines, each installed on a jacket with transition piece, anchored to the seabed by four steel pin piles.

The project, in particular the wind turbine installation campaign, has suffered significant delays due to restrictions and new regulations implemented by authorities in Taiwan and around the globe as a result of the COVID-19 pandemic.

Turbines with a downwind rotor

The TPC Offshore Wind Farm is constructed in a region where typhoons are very common. Consortium partner Hitachi Ltd. pioneered this design by obtaining the Wind Turbine Class T certification, an international standard on wind-resistant design recognising the need in regions subject to frequent typhoons.

The turbines are being installed by the Taillevent, specifically designed for the transport and installation of offshore wind turbines and foundations. The vessel measures approximately 140 m in length and is equipped with six spuds. She has an on-board crane with a lifting capacity of 1000 t and an auxiliary crane of 50 t.

Construction of Taiwan’s first state-owned offshore wind farm

Jan De Nul Group started the construction works for the offshore wind farm back in September 2018 with the preparatory onshore cable duct installation works to connect the existing onshore sub-station to the cable interface near shore.

In 2019, fabrication of the different components were initiated. In April 2020, the first foundation components were readied for transportation from the South Korean fabrication yards to the offshore windfarm area.

In June 2020, Jan De Nul Group installed the first pin piles and connected the first export cable to shore. And by early August, Jan De Nul Group installed and anchored the very first jacket foundation to the seabed.

About the Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration

The ‘Offshore Windfarm Phase 1 Project – Demonstration’ was awarded to the Consortium Jan De Nul – Hitachi in February 2018.

Jan De Nul Group is responsible for the design, fabrication and installation of the foundations, the provision of the offshore vessel for the installation of the wind turbines, the supply and installation of the cables off- and onshore as well as upgrading an electrical substation. Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the offshore wind turbines with downwind rotor.

Subsequently, the consortium is responsible for the operation and maintenance of the offshore wind farm over five years.


For more news and technical articles from the global renewable industry read our latest issue of Energy Global magazine.

Energy Global’s Summer 2020 issue

The Summer issue of Energy Global provides in-depth technical articles covering technological advancements and future outlooks in the renewables sector, from companies including Sulzer, Power Ledger, JinkoSolar, Trelleborg Applied Technologies, Clir Renewables, and many more. The issue covers a spectrum of clean energies, from wind to hydrogen to solar to biofuels.

Read the article online at: https://www.energyglobal.com/wind/21092020/jan-de-nul-group-installs-wind-turbine-for-tpc/