Fugro completes risk mitigation project for wind farm

Published by , Assistant Editor
Energy Global,


Fugro has successfully completed a second marine unexploded ordnance (UXO) risk mitigation project for TenneT on a cable route survey as part of the construction of the Hollandse Kust Zuid offshore wind farm.

The 13-month project involved surveying the route for explosive remnants of war (ERW), including munitions dumped at sea after conflict, and investigating potential targets. TenneT received their final UXO clearance certificate from Fugro once the cable route corridor was confirmed clear of UXO risk based on as low as reasonably practicable (ALARP) principles.

The project was delivered in two phases, starting with a complete cable route survey that utilised Fugro’s Geowing remotely operated towed vehicle and other equipment solutions to identify over 3600 potential targets of interest.

Following interpretation of these targets by Fugro’s UXO experts, over 700 potential ordnance (pUXO) targets were then investigated by Fugro’s UXO identification vessel, the Atlantis Dweller, before the route was declared free of UXO of the size and weight above the contracted threshold.

The Hollandse Kust Zuid wind farm, off the coast of The Hague and Noordwijk, will eventually supply green energy to up to 1.5 million homes.