Equis Australia secures approval for BESS
Published by Oliver Kleinschmidt,
Editorial Assistant
Energy Global,
The Lower Wonga battery energy storage system (BESS), located near Gympie in Queensland, has secured approval from Powerlink and AEMO to be connected to the national energy market. The project is being built, managed, and owned by Energy Infrastructure Australia, an Equis Australia company, which has been developing a portfolio of 17 battery projects across Australia totalling up to 4.4 GW of battery storage.
“The AUS$450 million BESS at Lower Wonga has a battery energy storage capacity of up to 200 MW and a discharge capacity of up to 800 MW/h, which is enough power to supply electricity for up to 53 000 homes for four hours,” said Mahesh Reddy Indluri, Managing Director at Equis Australia.
“The project will help to secure affordable, clean, and reliable electricity for Queensland’s future electricity demands. The BESS will create approximately 115 full-time jobs during construction and operations, and fund programmes targeting local needs considering feedback from the community.”
Reddy said the Lower Wonga BESS would allow for more solar and wind energy to be integrated into the grid, helping to reduce grid volatility, lower electricity prices and the need for expensive new power stations.
“The BESS would be connected to Queensland’s electricity grid via a transmission line that connects to the 275 kV Woolooga Substation,” according to Roby Camagong, Investment Director at Equis Australia.
“Making the transition from fossil fuels to ‘baseload’ renewables, the ability to store and dispatch energy will play a key support role to provide rapid-response services to grid contingency events such as outages or heat waves.
“Grid scale battery storage fills this key short-term role,” Camagong added.
Equis participated in the annual Fraser Coast and Gympie Regional Projects Industry Briefing and has been looking forward to partnering with local and regional businesses to deliver the project. Camagong said the BESS project would provide significant local benefits during construction and operation, including investment in the local economy.
“We will be in a position to start work later this year and be operational by 2026.
“Across Australia, Equis is committed to investing in and delivering renewable assets that will support Australians and the local communities in which they live for generations to come,” Camagong continued.
Reddy said Equis is developing a pipeline of high-quality battery storage and wind generation projects in Queensland, including the recently announced Jackson North Wind Farm in Woleebee, Queensland.
In November 2023, Equis and the Victorian Government’s SEC financially closed and commenced construction of Phase 1 of the Melbourne Renewable Energy Hub. Once complete, MREH will provide 1.6 GW/h of energy storage, enough to power up to 200 000 homes during peak periods.
For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.
Energy Global's Summer 2024 issue
The Summer 2024 issue of Energy Global starts with a guest comment from Terrawatt on the streamlining of the permitting process in Italy, before moving on to a regional report from Frost & Sullivan on the energy landscape in Asia Pacific. This issue looks at key topics such as wind installation vessels, offshore wind turbine foundations, weather analysis, solar maintenance, and more!
Read the article online at: https://www.energyglobal.com/energy-storage/07082024/equis-australia-secures-approval-for-bess/
You might also like
An evolution in wind energy
Stefano Santoni, Davi, Italy, examines the need for offshore and onshore wind turbine components to meet increasing demand in the wake of the growth of wind energy.