Jones Bros to construct battery storage project

Published by , Editor
Energy Global,


A leading civil engineering firm is undertaking the construction of one of the UK’s largest battery storage projects to-date.

Jones Bros Civil Engineering UK has been engaged by Quinbrook Infrastructure Partners and E.ON to carry out the multi-million-pound contract at Uskmouth in South Wales.

The 230 MW battery energy storage system (BESS) scheme is expected to be operational in 1Q25 and will be a key contributor to achieving the country’s net-zero targets of decarbonising all sectors of the economy by 2050.

Having completed the enabling works at the site of a former coal-fired power station, with activity including creating the compound and erecting acoustic fencing, the Jones Bros team has been building the main platform.

Approximately 74 000 m3 of aggregate was imported by rail to ensure that it was above the flood plain. The platform also features four impermeable cells that help capture water and distribute it to an attenuation pond.

Activity is currently focused on foundations for the battery and power conversion systems (PCS) units, as well as the primary and secondary substations and transformers.

A fly ash tunnel that is part of the existing infrastructure will be cleaned out and repurposed for the housing of cables and electrical components, before ducting work is undertaken.

As part of the ecological enhancement plan, that includes creating a sustainable energy park, new fencing will be installed and landscaping carried out to help make it more appealing to wildlife such as otters and water voles.

Jones Bros Contacts Manager, Rhys Roberts, said: “It’s a fantastic scheme to be a part of as the country’s energy transition gathers speed.

“Helping turn a former coal-fired power station site into one that will play a significant role in supporting sources of renewable energy is wonderful for us as a company.”

The project uses existing infrastructure such as the grid connection, industrial water supplies, and railway access to deliver key components.

Expected reduction in road transportation across the construction activity is 230 000 miles.

Rhys continued: “We are always eager to minimise impact on the local area, so being able to utilise aspects like the railway for the aggregate and transporting the 20 ft containers full of battery units to site is great.

“We are also turning a pre-existing garage from the old power station into a welfare building, with the target of making it Building Research Establishment Environmental Assessment Method (BREEAM) rating excellent.

“We are currently achieving that as part of our activity, which is due to be completed towards the end of the year.”

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Summer 2024 issue

The Summer 2024 issue of Energy Global starts with a guest comment from Terrawatt on the streamlining of the permitting process in Italy, before moving on to a regional report from Frost & Sullivan on the energy landscape in Asia Pacific. This issue looks at key topics such as wind installation vessels, offshore wind turbine foundations, weather analysis, solar maintenance, and more!

Read the article online at: https://www.energyglobal.com/energy-storage/30072024/jones-bros-to-construct-battery-storage-project/

You might also like

 
 

Embed article link: (copy the HTML code below):