Cornwall Insight: CfD AR4 onshore wind and solar pipeline reaches 8 GW

Published by , Assistant Editor
Energy Global,


The latest figures from Cornwall Insight’s renewables pipeline tracker shows that both the onshore wind and solar pipelines continue to grow. Cornwall Insight calculates a Contracts for Difference (CfD) Allocation Round 4 (AR4) eligible solar pipeline of approximately 3 GW, up by approximately 1.8 GW on the same time 12 months ago, with CfD eligible onshore wind capacity at approximately 5 GW, up by around 1 GW over the same period.

Further analysis also shows at least a further approximately 6 GW of solar photovoltaic (PV) capacity is in the grid connection queue and not yet in planning.

James Brabben, Head of Assets and Infrastructure at Cornwall Insight, said:

“With around four months to go until eligibility deadlines, the pipeline could increase further, especially from solar PV with its typically quicker lead times for planning approval.

“By December, we could therefore have a record level of new-build renewables looking to bid into the CfD round, creating some interesting decisions for new-build plants.

“Depending on budget and MW cap parameters in the auction, some projects may deem it unlikely they will be competitive in the CfD. As a result, they may look to alternative routes to market options such as utility Power Purchase Agreements (PPAs) or Corporate PPAs (CPPAs).

“Some generators may also look to find an edge by incorporating other revenues, including those available through balancing services markets or different business models such as co-location with batteries.

“Although there are alternative options available to new-build generators, these are still challenging, and the bankability of the CfD contract is likely to incentivise solar and onshore wind generators to bid into the AR4 process. The lack of costs or bid bonds in AR4 participation would also support this view, with generators potentially seeing the auction as a free hit to enter and find out if prices materialise at a level suitable for their project returns.

“We, therefore, expect very high levels of auction competition and a potential stalling in the development of other routes to market options such as utility PPAs and CPPAs if generators crowd the CfD and only look at alternatives post-auction in spring/summer 2022.”

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Summer 2021 issue

The Summer issue of Energy Global features a varied spectrum of in-depth technical articles detailing recent projects, future projections, and technological advancements in the renewables sector, from companies including CEWEP, Enel Green Power, Turboden S.p.A., Cornwall Insight, and more.

Don’t forget to sign up to receive future digital issues of Energy Global for free here.

Read the article online at: https://www.energyglobal.com/special-reports/27082021/cornwall-insight-cfd-ar4-onshore-wind-and-solar-pipeline-reaches-8-gw/