RWE awards DeepOcean contract for Nordseecluster A

Published by , Editor
Energy Global,


Ocean services provider, DeepOcean, has received a firm order for RWE’s Nordseecluster A offshore wind project in Germany. DeepOcean’s scope of work includes trenching, transport, and installation of all inter-array cables with adjacent services for all wind turbines of Nordseecluster A.

RWE has recently made the final investment decision for its entire Nordseecluster, involving offshore wind projects with a total capacity of 1.6 GW. The Nordseecluster will be constructed in two phases: Nordseecluster A and Nordseecluster B. The wind farms will be built in the German North Sea, about 50 km north of the island of Juist.

In August 2023, RWE announced that DeepOcean had been chosen as its preferred supplier of subsea installation services for the Nordseecluster A.

DeepOcean has now been awarded a firm order that will include preparatory work, transport and installations of all inter-array cables, including trenching, topside pull-ins and terminations for the initial build-out phase. In total, DeepOcean will install 185 kilometres of 66 kV aluminium and copper cables to connect all 44 offshore wind turbines of Nordseecluster A.

“We look forward to mobilising a complete engineering, project management and execution team that will support RWE on this important offshore wind development which will contribute to the decarbonisation of European industry. RWE is one of the world’s leading players in offshore wind and this significant contract award will draw on a broad set of our expertise,” said Øyvind Mikaelsen, CEO of DeepOcean.

Nordseecluster A has a total capacity of 660 MW. Construction at sea is scheduled to begin next year. By the beginning of 2027, all wind turbines shall be connected to the grid. The second phase, Nordseecluster B, will add a further 900 MW of capacity, with commercial operation expected to begin in early 2029.

DeepOcean’s scope of work also includes project management and engineering; offshore preparation work including pre-installation cable route survey, route engineering and burial assessment, boulder relocation, foundation preparatory work and offshore substation preparatory work; transport and installation of inter-array cables including burial, pull-in, monitoring and testing; as well as seabed surveys and monitoring.

Project management will be based out of Aberdeen, with support functions provided across DeepOcean’s UK and Norway offices. DeepOcean’s offshore preparations and pre-installation surveys will commence in 2Q25, with the main works commencing in the beginning of 2026. DeepOcean will utilise three vessels for the project.

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Summer 2024 issue

The Summer 2024 issue of Energy Global starts with a guest comment from Terrawatt on the streamlining of the permitting process in Italy, before moving on to a regional report from Frost & Sullivan on the energy landscape in Asia Pacific. This issue looks at key topics such as wind installation vessels, offshore wind turbine foundations, weather analysis, solar maintenance, and more!

Read the article online at: https://www.energyglobal.com/wind/03072024/rwe-awards-deepocean-contract-for-nordseecluster-a/