Skip to main content

Enefit Green begins Purtse hybrid park installation

Published by , Editor
Energy Global,


The first wind turbine in Enefit Green’s wind and solar hybrid park in Purtse has been constructed. The installation of solar panels started week commencing 30 January 2023.

Enefit Green is building Estonia's first wind and solar hybrid park in Lüganuse Parish. Five wind turbines with a total capacity of 21 MW will be erected in the wind farm. A solar park with 49 000 panels and a total capacity of 32 MW will also be built in the same area.

Both parks use the same equipment, substation, connection, and connection capacity to bring the electricity produced from wind and solar to consumers. Since the period from Autumn to Spring is the best time for wind power production, and Spring to Autumn for solar power production, the electricity output of a hybrid plant is more consistent throughout the year and the network is better utilised.

According to Janek Lillemägi, Senior Project Manager at Enefit Green, the assembly of wind turbines goes quickly when the weather is good: “If strong winds don’t interfere with the work, a wind turbine can be assembled in two days. The lower tower sections have been placed in all positions. Now the installation of the upper sections with a higher crane continues, followed by lifting the nacelles to the tops and fixing the blades.”

According to him, the transport of nearly 70-m wind turbine blades from the port of Paldiski to the wind farm area was successful. “A total of 15 blades completed the journey of more than 200 km without incident. The towers and nacelles of the wind turbines were also successfully delivered. We are on time with the schedule of sending the first amount of electricity from Purtse to the power network in the spring,” he added.

The construction of the solar park in Purtse is proceeding according to the planned schedule. According to Project Manager, Rainer Tammus, a lot of different jobs are taking place at the construction site at the same time, and despite delivery difficulties, all important materials have arrived at the site on time.

“The construction of the base frames for solar panels is nearing the finish line and the installation of nearly 49 000 panels has begun, lasting until the end of March. Almost 70 people are working on the site every day so that we are ready for the peak time for production,” Tammus commented.

Five Vestas V136 wind turbines with a tower height of 82 m and a peak height of 150 m are being installed in the Purtse wind farm area. These are the first Vestas wind turbines to come directly from the factory to be erected in Estonia.

The Yingli Solar solar panels used in the hybrid park have a capacity of 655 W each. These are double-sided panels that can use the energy reflected on the back side as well.

 

 

For more news and technical articles from the global renewable industry, read the latest issue of Energy Global magazine.

Energy Global's Winter 2022 issue

The Winter 2022 issue of Energy Global hosts an array of technical articles focusing on wind, solar, energy storage, geothermal, and more. This issue also features a regional report on the Australian renewables sector.

Read the article online at: https://www.energyglobal.com/wind/06022023/enefit-green-begins-purtse-hybrid-park-installation/

You might also like

 
 

Embed article link: (copy the HTML code below):